CPIM practice test: 30 exam questions across version 9.0

Certified in Planning and Inventory Management · Association for Supply Chain Management (ASCM)

Every figure below names its document; this page draws on 6 documents, last checked Nov 18, 2026.

This CPIM practice test holds 30 exam questions, each tagged to one area of the nine in ASCM's current content manual, ECM 9.0. Each one has 4 choices, the format ASCM uses, and once you commit to an answer, a note opens under each option. There is no sign-up; work through it at one go or a handful at a time. 1 6

Parts of this page 8 parts
  1. How the set follows the content manual
  2. The set, with an area chip on every item 30
  3. Using the explanations
  4. An independent question set, not ASCM's
  5. Where to go after the set
  6. More free sets on this site
  7. Before you start the set 3
  8. The documents behind this page

How the set follows the content manual

The set follows ASCM's area weights roughly: about four questions for each of the larger areas, two or three for the smaller ones. Every question carries a chip naming its area, so a weak spot shows up by area rather than as one overall number.

Several items ask you to work out a number rather than recognize a term. All the data sits in the question itself, written out in sentences rather than in a grid.

The set, with an area chip on every item

Tally: 0/30 tried, 0 on the key
II S&OP · 10% Question 1 of 30

Which sequence of these monthly S&OP steps is correct?

Choose a letter to record your answer; each option then opens with its reasoning.

  1. Supply review, demand review, reconciliation, executive S&OP Check A
    Off the key. Reviewing supply first tests capacity against last month's demand picture; supply responds to the updated demand plan, so it comes second.
  2. Demand review, reconciliation, supply review, executive S&OP Check B
    Off the key. Reconciling before the supply review leaves nothing to reconcile, because the capacity and material view of the demand plan does not exist yet.
  3. Demand review, supply review, reconciliation, executive S&OP Check C
    This is the keyed answer. Demand is reviewed first so supply has an updated plan to test; the gaps between the two are then reconciled, and the executive S&OP meeting makes the final calls.
  4. Reconciliation, demand review, supply review, executive S&OP Check D
    Off the key. Opening with reconciliation puts the balancing step ahead of both plans it is meant to balance.
You chose—
Key—
Outcome—

Study notes for this area: S&OP

IV Internal supply · 12% Question 2 of 30

A routing change cuts product P's time at WC-10 from 15 to 10 standard minutes per unit. WC-10 has 160 hours available a week, 100% utilization and 90% efficiency. How many units of P can WC-10 now produce in a week?

  1. 864 units Check A
    This is the keyed answer. Weekly standard minutes are 160 × 60 × 1.00 × 0.90 = 8,640; at the new 10 minutes per unit, WC-10 makes 864 units.
  2. 960 units Check B
    Off the key. 960 divides the full 9,600 minutes by 10 but ignores the 90% efficiency, so it overstates output.
  3. 576 units Check C
    Off the key. 576 applies the 90% efficiency to the old 15-minute standard; the routing change cut the time to 10 minutes.
  4. 640 units Check D
    Off the key. 640 uses the old 15-minute standard and leaves out efficiency, so it misses both the routing change and the 90% factor.
You chose—
Key—
Outcome—

Study notes for this area: Internal supply

VII Detailed schedules · 12% Question 3 of 30

Operation D takes 6.2 standard minutes per unit, and daily demand is 100 units. Its work center runs two 8-hour shifts at full utilization: shift 1 at 95% efficiency and shift 2 at 85%. What is operation D's load as a percentage of daily rated capacity?

  1. 71.8% Check A
    This is the keyed answer. Rated capacity is 480 × 0.95 + 480 × 0.85 = 864 standard minutes and the load is 6.2 × 100 = 620 minutes, so the load is 620 ÷ 864 = 71.8%.
  2. 64.6% Check B
    Off the key. 64.6% divides the 620-minute load by the 960 clock minutes and ignores the efficiency of both shifts.
  3. 76.0% Check C
    Off the key. 76.0% applies the second shift's 85% to both shifts, though the first shift runs at 95%.
  4. 68.0% Check D
    Off the key. 68.0% applies 95% efficiency to both shifts, but the second shift runs at only 85%.
You chose—
Key—
Outcome—

Study notes for this area: Detailed schedules

I Strategy · 12% Question 4 of 30 Maturity

A supply chain maturity assessment places a company at the lowest stage. Which description best fits that stage?

  1. Plans are shared with key suppliers and customers Check A
    Off the key. Sharing plans with key suppliers and customers comes after internal integration, so it marks an advanced stage.
  2. Internal plans are integrated through S&OP Check B
    Off the key. Integrating internal plans through S&OP is a later stage, reached once functions plan together.
  3. Functions optimize separate local metrics in silos Check C
    This is the keyed answer. At the lowest maturity stage each function works to its own measures, such as purchase price or plant utilization, with little coordination across them.
  4. Network-wide planning is synchronized in real time Check D
    Off the key. Real-time synchronization across the whole network describes the most advanced stage, not the lowest.
You chose—
Key—
Outcome—

Study notes for this area: Strategy

I Strategy · 12% Question 5 of 30

A mature product line enters the decline stage of its life cycle. Which supply chain action is most appropriate?

  1. Expand distribution into new channels Check A
    Off the key. Opening new channels is a growth-stage move to reach new buyers; in decline it adds cost for falling volume.
  2. Invest in new features and variants Check B
    Off the key. Adding features and variants widens the range just as demand falls, which raises inventory and obsolescence risk.
  3. Add capacity to defend market share Check C
    Off the key. New capacity in a shrinking market would sit idle; decline calls for reducing and consolidating capacity.
  4. Reduce inventory and prune weak SKUs Check D
    This is the keyed answer. In decline, demand shrinks, so the supply chain lowers stock to avoid obsolescence and drops low-volume SKUs that no longer cover their cost.
You chose—
Key—
Outcome—

Study notes for this area: Strategy

I Strategy · 12% Question 6 of 30

A fashion retailer supplies short-life, trend-driven products through a supply chain optimized for lowest cost, with long offshore lead times and large production lots. What result is most likely?

  1. Low obsolescence and steady margins Check A
    Off the key. Trend products on long lead times are highly exposed to obsolescence, and the markdowns that follow erode margin.
  2. Frequent stockouts and heavy markdowns Check B
    This is the keyed answer. Long, cost-driven lead times force early, large commitments on trend products, so the hits sell out (stockouts) and the misses are cleared at heavy markdowns.
  3. Stable service at the lowest landed cost Check C
    Off the key. The unit cost is low, but service swings because the chain cannot react to what actually sells, and markdowns eat the savings.
  4. Low inventory and high inventory turns Check D
    Off the key. Large offshore lots of short-life goods build stock rather than lowering it, so inventory turns fall.
You chose—
Key—
Outcome—

Study notes for this area: Strategy

I Strategy · 12% Question 7 of 30

A plant uses the same flexible equipment and skilled staff to make several related products at a lower total cost than separate dedicated plants would. This is an example of:

  1. economies of scope. Check A
    This is the keyed answer. Sharing flexible equipment and skills across several related products to cut total cost is the definition of economies of scope.
  2. the learning curve effect. Check B
    Off the key. The learning curve is the falling time per unit as cumulative output of a task grows, not a saving from sharing resources across products.
  3. vertical integration. Check C
    Off the key. Vertical integration means owning more stages of the chain, such as suppliers or distributors; nothing in the plant's ownership changes here.
  4. economies of scale. Check D
    Off the key. Economies of scale come from making more of one product so fixed cost is spread wider; here the saving comes from variety on shared resources.
You chose—
Key—
Outcome—

Study notes for this area: Strategy

II S&OP · 10% Question 8 of 30

The executive S&OP meeting is held in week 3, after next month's production commitments are already locked. As a result, trade-offs are decided in ad-hoc meetings. Which change best fixes this?

  1. Hold the executive meeting quarterly instead Check A
    Off the key. A quarterly executive meeting makes decisions even less frequent and leaves the timing conflict in place.
  2. Improve the statistical forecasting model Check B
    Off the key. Improving the forecasting model does not change when decisions are made; the trade-offs still arrive after commitments are fixed.
  3. Add a weekly checkpoint to the monthly supply review Check C
    Off the key. Another supply checkpoint adds meetings but still leaves decisions that need executive authority with no forum before the lock.
  4. Move the executive meeting earlier in the month Check D
    This is the keyed answer. The executive meeting exists to settle trade-offs, so it has to come before production commitments lock; held after the lock, its decisions move to ad-hoc meetings.
You chose—
Key—
Outcome—

Study notes for this area: S&OP

II S&OP · 10% Question 9 of 30

Beginning inventory is 500 units. Monthly demand for six months is 1,000, 1,200, 1,400, 1,600, 1,400 and 1,200 units. Production is level at average monthly demand plus 10%. What is the inventory at the end of month 6?

  1. 500 units Check A
    Off the key. 500 is the beginning inventory; producing above average demand builds stock over the six months.
  2. 1,430 units Check B
    Off the key. 1,430 is the monthly production rate, not the inventory left after six months.
  3. 780 units Check C
    Off the key. 780 counts the 10% surplus (6 × 130) but leaves out the 500 units of beginning inventory.
  4. 1,280 units Check D
    This is the keyed answer. Average demand is 7,800 ÷ 6 = 1,300, so level output is 1,430 a month, and 500 + 6 × 1,430 − 7,800 = 1,280 units remain at the end of month 6.
You chose—
Key—
Outcome—

Study notes for this area: S&OP

III Demand · 12% Question 10 of 30

A company has 2,400 of its machines in the field. Each needs a pump replacement on average every 4 years, and the company wins 75% of that replacement business. What is the annual service demand for pumps?

  1. 800 units Check A
    Off the key. 800 assumes a three-year replacement cycle instead of four and also ignores the 75% share.
  2. 450 units Check B
    This is the keyed answer. 2,400 machines needing a pump every 4 years make 600 replacements a year, and a 75% share of them is 450 pumps.
  3. 600 units Check C
    Off the key. 600 is every replacement in the field per year; the company wins only 75% of that business.
  4. 1,800 units Check D
    Off the key. 1,800 is 75% of the installed base, as if every machine needed a new pump each year.
You chose—
Key—
Outcome—

Study notes for this area: Demand

III Demand · 12% Question 11 of 30

Demand review data for six months — forecast: 120, 130, 125, 140, 135, 150; actual: 110, 115, 120, 130, 140, 160. Using error = actual − forecast, which result is correct?

  1. CFE +25, MAD 9.17: forecast biased low Check A
    Off the key. CFE +25 flips the sign: with error defined as actual − forecast, the errors sum to −25.
  2. CFE −25, MAD −4.17: forecast biased high Check B
    Off the key. MAD averages absolute errors and cannot be negative; −4.17 is the signed average error, the CFE divided by 6.
  3. CFE −25, MAD 9.17: forecast biased low Check C
    Off the key. The two figures are right, but a negative CFE under actual − forecast means the forecast was too high, not too low.
  4. CFE −25, MAD 9.17: forecast biased high Check D
    This is the keyed answer. Errors are −10, −15, −5, −10, +5, +10, so CFE = −25 and MAD = 55 ÷ 6 = 9.17; a negative sum of actual minus forecast means forecasts ran above actual.
You chose—
Key—
Outcome—

Study notes for this area: Demand

III Demand · 12% Question 12 of 30

Product A has MAD = 20 units and MAPE = 10%. Product B has MAD = 40 units and MAPE = 8%. Which statement is correct?

  1. B has smaller unit errors but worse relative accuracy Check A
    Off the key. This reverses both facts: B has the larger MAD and the smaller MAPE.
  2. B has larger unit errors and worse relative accuracy Check B
    Off the key. B's unit errors are larger, but a lower MAPE means better relative accuracy, not worse.
  3. A has smaller unit errors and better relative accuracy Check C
    Off the key. A does have the smaller unit errors, but its 10% MAPE is higher than B's 8%, so A's relative accuracy is worse.
  4. B has larger unit errors but better relative accuracy Check D
    This is the keyed answer. B's MAD of 40 units is twice A's, yet its 8% MAPE is below A's 10%, so B is the more accurate relative to its volume.
You chose—
Key—
Outcome—

Study notes for this area: Demand

III Demand · 12% Question 13 of 30

Sales of heavy trucks rise and fall over four- to six-year periods that follow the economy. This pattern is the:

  1. cyclical component. Check A
    This is the keyed answer. Rises and falls over several years that track the economy are the cyclical component of demand.
  2. seasonal component. Check B
    Off the key. A seasonal pattern repeats within a year, such as monthly or quarterly peaks, not over four- to six-year periods.
  3. random component. Check C
    Off the key. Random variation has no pattern; a swing that repeats with the business cycle is not random.
  4. trend component. Check D
    Off the key. Trend is a steady long-run rise or fall; demand that rises and then falls again over years is cyclical.
You chose—
Key—
Outcome—

Study notes for this area: Demand

IV Internal supply · 12% Question 14 of 30

A supplier always ships the right quantity but its delivery dates vary by up to a week; demand for the item is stable. Which MRP buffer fits this uncertainty best?

  1. A larger lot size Check A
    Off the key. A bigger lot changes how often the item is ordered, not when each order arrives, so a late delivery still leaves a gap.
  2. Planned safety lead time Check B
    This is the keyed answer. Safety lead time targets the timing variation itself: when quantities are reliable but dates slip, orders are planned to arrive earlier by a set margin.
  3. Safety stock Check C
    Off the key. Safety stock is the buffer for uncertainty in quantity; when quantities are exact and only dates vary, it protects the wrong dimension.
  4. A longer planning time fence Check D
    Off the key. The planning time fence limits automatic replanning by MRP; it does nothing about a supplier's late deliveries.
You chose—
Key—
Outcome—

Study notes for this area: Internal supply

IV Internal supply · 12% Question 15 of 30

MRP suggests an order for 300 units. A tooling limit allows only 250, so the quantity is cut, but the next MRP run resets it to 300. The order is not ready for release. What is the right step?

  1. Change the item's order policy to lot-for-lot Check A
    Off the key. A lot-for-lot order policy changes how every future order for the item is sized and does not hold this one at 250.
  2. Convert it to a firm planned order Check B
    This is the keyed answer. A firm planned order keeps the planner's 250 units and date: MRP will not reset it on the next run, and the order stays unreleased.
  3. Record it as a scheduled receipt Check C
    Off the key. A scheduled receipt is an order already released; recording it that way misstates an order that is not ready for release.
  4. Lower the parent's gross requirement Check D
    Off the key. Cutting the parent's requirement to fit a tooling limit falsifies the demand picture, and MRP would still resize the order next run.
You chose—
Key—
Outcome—

Study notes for this area: Internal supply

IV Internal supply · 12% Question 16 of 30

FG has a customer order for 150 units. Each FG needs 2 of A, and each A needs 3 of purchased part C. A has 10% scrap, so A build quantities are divided by 0.9 and rounded up. C has 100 on hand and a scheduled receipt of 50. What is the net requirement for C?

  1. 852 units Check A
    This is the keyed answer. FG needs 300 of A; 300 ÷ 0.9 = 333.3, rounded up to 334 starts; 334 × 3 = 1,002 of C, less 100 on hand and the 50 scheduled = 852.
  2. 1,002 units Check B
    Off the key. 1,002 is the gross requirement for C; on-hand stock and the scheduled receipt still have to be netted off.
  3. 902 units Check C
    Off the key. 902 subtracts the stock on hand but forgets the 50-unit scheduled receipt.
  4. 750 units Check D
    Off the key. 750 nets off both supplies but ignores A's 10% scrap: 900 − 150 = 750.
You chose—
Key—
Outcome—

Study notes for this area: Internal supply

V External supply · 11% Question 17 of 30

Compared with single sourcing, what is the main disadvantage of splitting a component between two suppliers?

  1. Longer recovery after a disruption Check A
    Off the key. Splitting volume does not slow recovery after a disruption; what the buyer gives up is price, because each supplier's smaller share earns less discount.
  2. Greater exposure to one supplier's failure Check B
    Off the key. With two suppliers each holding part of the volume, exposure to either one's failure goes down, not up.
  3. Less competition and weaker price pressure Check C
    Off the key. Two active suppliers competing for share add competition rather than reduce it.
  4. Less volume leverage and higher unit cost Check D
    This is the keyed answer. Splitting the volume gives each supplier a smaller share, so the buyer loses volume discounts and often pays a higher unit price.
You chose—
Key—
Outcome—

Study notes for this area: External supply

V External supply · 11% Question 18 of 30

Which activity is part of strategic sourcing rather than day-to-day purchasing?

  1. Matching invoices and receipts Check A
    Off the key. Checking invoices against goods received is a routine step of paying for orders, part of daily purchasing.
  2. Expediting a late shipment Check B
    Off the key. Chasing a late shipment is day-to-day follow-up on an order already placed.
  3. Category spend and market analysis Check C
    This is the keyed answer. Analyzing spend by category and how the supply market works is the groundwork of strategic sourcing, done before suppliers and contracts are chosen.
  4. Issuing releases against a blanket order Check D
    Off the key. Releases against a blanket order are routine transactions under an agreement already negotiated.
You chose—
Key—
Outcome—

Study notes for this area: External supply

VI Inventory · 14% Question 19 of 30 Disposition

Finished goods are obsolete in their original market but still fully usable. Which disposition should normally be considered first?

  1. Recycle their materials Check A
    Off the key. Recycling recovers only material value, so it comes after options that keep the product whole.
  2. Scrap them for a tax write-off Check B
    Off the key. Scrapping usable goods destroys their remaining value, which makes it the last option, not the first.
  3. Resell them via a second channel Check C
    This is the keyed answer. Goods that still work keep value in another market, such as a secondary or export channel, so reselling recovers the most before lower-value options.
  4. Hold them in case demand returns Check D
    Off the key. Holding obsolete stock adds carrying cost while its value keeps falling, and demand in the original market has ended.
You chose—
Key—
Outcome—

Study notes for this area: Inventory

VI Inventory · 14% Question 20 of 30

Cycle counts show repeated shortages of small, high-value items stored near an unsecured shipping dock. What should the inventory manager do first?

  1. Count those items more often Check A
    Off the key. Extra counts add labor on items whose counts already point to the open dock as the source of the shortages.
  2. Adjust the records to match the counts Check B
    Off the key. Adjusting records makes the books agree with the shelf but leaves the cause in place, so the shortages return at the next count.
  3. Raise safety stock on those items Check C
    Off the key. Extra safety stock puts more items at risk and does nothing about where they are going.
  4. Restrict access to those items Check D
    This is the keyed answer. Repeated shortages of small, valuable items next to an open dock point to theft, so controlling access treats the cause instead of the symptom.
You chose—
Key—
Outcome—

Study notes for this area: Inventory

VI Inventory · 14% Question 21 of 30

A planner sets safety stock as z × σ × √LT, where σ is the standard deviation of daily demand and LT is the lead time in days. Daily demand has a standard deviation of 50 units, the replenishment lead time is 16 days, and z = 1.65. How much safety stock is needed?

  1. 330 units Check A
    This is the keyed answer. σ over the lead time is 50 × √16 = 200 units, and 1.65 × 200 = 330 units of safety stock.
  2. 1,320 units Check B
    Off the key. 1,320 multiplies by the 16 days instead of their square root; daily variation does not add up linearly over time.
  3. 82.5 units Check C
    Off the key. 82.5 is 1.65 × 50, one day of protection, with no allowance for the 16-day lead time.
  4. 200 units Check D
    Off the key. 200 is the standard deviation over the lead time before the z factor of 1.65 is applied.
You chose—
Key—
Outcome—

Study notes for this area: Inventory

VI Inventory · 14% Question 22 of 30

A cycle count finds 3,450 units against a record of 3,680. Investigation shows that a receipt of 150 units was never recorded. How many units of unrecorded issues or losses remain to be explained?

  1. 230 units Check A
    Off the key. 230 is the raw gap between record and count; the unrecorded receipt means the true shortfall is larger.
  2. 380 units Check B
    This is the keyed answer. After the missed receipt the record should read 3,680 + 150 = 3,830, and 3,830 − 3,450 = 380 units are still unexplained.
  3. 150 units Check C
    Off the key. 150 is the receipt that was found; it shows the record was too low, so it is not part of the loss.
  4. 80 units Check D
    Off the key. 80 subtracts the receipt from the gap (230 − 150), but a missed receipt understates the record, so it adds to the loss.
You chose—
Key—
Outcome—

Study notes for this area: Inventory

VII Detailed schedules · 12% Question 23 of 30

Before buying a second paint booth, planners want to see how variable arrivals and random breakdowns would affect queues and throughput in the redesigned flow. Which tool fits best?

  1. Rough-cut capacity check Check A
    Off the key. A rough-cut capacity check compares total load on key resources with capacity, without queue or breakdown dynamics.
  2. Discrete-event simulation Check B
    This is the keyed answer. Simulation plays out each arrival and breakdown as a random event over time, so it shows the queues and throughput that variability creates.
  3. Linear regression model Check C
    Off the key. Regression fits a relationship to past data; it does not model how random arrivals and failures interact in a redesigned flow.
  4. Average-capacity spreadsheet Check D
    Off the key. A spreadsheet of averages hides the variability that builds queues, so it shows the new flow running more smoothly than it will.
You chose—
Key—
Outcome—

Study notes for this area: Detailed schedules

VII Detailed schedules · 12% Question 24 of 30

A planner splits a 1,000-unit order into releases of 400 and 600 units so that 400 can ship in week 1. Compared with a single release, what is the main added cost?

  1. An extra setup at each operation Check A
    This is the keyed answer. Two lots mean two setups at every operation on the routing, which is the main cost of splitting.
  2. A higher standard material cost Check B
    Off the key. Standard material per unit is the same whether 1,000 units run as one lot or two.
  3. A longer queue for the first lot Check C
    Off the key. The 400-unit lot is moved ahead to ship in week 1, so its wait shrinks rather than grows.
  4. More run time per unit produced Check D
    Off the key. Run time per unit belongs to the operation and does not change; splitting adds setups, not run time.
You chose—
Key—
Outcome—

Study notes for this area: Detailed schedules

VII Detailed schedules · 12% Question 25 of 30

A line must produce 360 units in a 7.5-hour day. The total work content is 460 seconds per unit, and after balancing the line uses 7 stations. What is the balance efficiency?

  1. 87.6% Check A
    This is the keyed answer. Cycle time is 27,000 s ÷ 360 = 75 s, so efficiency is 460 ÷ (7 × 75) = 460 ÷ 525 = 87.6%.
  2. 82.1% Check B
    Off the key. 82.1% uses an 8-hour day and an 80-second cycle instead of the stated 7.5 hours and 75 seconds.
  3. 114.1% Check C
    Off the key. 114.1% inverts the ratio; efficiency is work content divided by total station time and cannot exceed 100%.
  4. 12.4% Check D
    Off the key. 12.4% is the balance delay, the idle share of station time, which is 100% minus the efficiency.
You chose—
Key—
Outcome—

Study notes for this area: Detailed schedules

VIII Distribution · 8% Question 26 of 30

The transit lead time in a branch's DRP record is 3 days, but goods actually spend 6 days in transit. What is the most likely result?

  1. Many reschedule-out messages are generated Check A
    Off the key. Late arrivals cause shortages that call for reschedule-in or expedite action, not reschedule-out.
  2. Branch stock builds up above its target Check B
    Off the key. Late arrivals drain branch stock below target, the opposite of a buildup.
  3. Shipments are released too late for need Check C
    This is the keyed answer. DRP offsets each planned shipment by the recorded 3 days, so with a real 6-day transit every shipment lands about 3 days late.
  4. Central DC gross requirements are overstated Check D
    Off the key. The transit lead time sets when the central DC's requirements fall, not how large they are.
You chose—
Key—
Outcome—

Study notes for this area: Distribution

IX Quality, CI & technology · 9% Question 27 of 30 APS

Compared with traditional MRP and CRP, what is the key advantage of an advanced planning and scheduling (APS) system for detailed scheduling?

  1. It schedules each work center independently Check A
    Off the key. Scheduling work centers one at a time misses how they interact; APS schedules across resources together.
  2. It uses fixed planned lead times for every order Check B
    Off the key. Fixed planned lead times are an MRP assumption; APS derives lead times from the actual load and sequence.
  3. It plans material and capacity at once, finitely Check C
    This is the keyed answer. APS checks material and capacity constraints together and schedules within finite capacity, so the plan is feasible when it is released.
  4. It loads infinitely, and planners level by hand Check D
    Off the key. Infinite loading with leveling by hand is how MRP and CRP work, the approach APS replaces.
You chose—
Key—
Outcome—

Study notes for this area: Quality, CI & technology

IX Quality, CI & technology · 9% Question 28 of 30 OEE

A machine's OEE falls from 80% to 68%, while its availability and quality rates are unchanged. Which loss most likely increased?

  1. Breakdowns and changeovers Check A
    Off the key. Breakdowns and changeovers are downtime, so they would lower availability, which did not change.
  2. Minor stops and slowed cycles Check B
    This is the keyed answer. With availability and quality unchanged, the drop must come from the performance factor, which is lost to minor stops and running below ideal speed.
  3. Scrap and rework Check C
    Off the key. Scrap and rework cut the quality rate, which stayed the same.
  4. Planned maintenance shutdowns Check D
    Off the key. Planned shutdowns are taken out of planned production time before OEE is figured, so they do not move it.
You chose—
Key—
Outcome—

Study notes for this area: Quality, CI & technology

VIII Distribution · 8% Question 29 of 30

A central DC will be short of an item in week 5. Which DRP capability shows the planner which branches' planned orders make up the DC's week-5 demand?

  1. Bill of distribution Check A
    Off the key. The bill of distribution maps which branches the DC supplies, but not which planned orders make up a given week's requirement.
  2. Time-phased order point Check B
    Off the key. Time-phased order point is a method for planning independent-demand items over time, not a trace of a requirement's sources.
  3. Pegged requirements Check C
    This is the keyed answer. Pegging traces the DC's gross requirement back to the branch planned orders that create it, so the planner sees whose demand makes up week 5.
  4. Action messages Check D
    Off the key. Action messages tell the planner to release, expedite, or reschedule an order; they do not show where a requirement came from.
You chose—
Key—
Outcome—

Study notes for this area: Distribution

V External supply · 11% Question 30 of 30

A component supplier completes the buyer's certification program after a long run of defect-free lots and a review of its process controls. What does the certification most directly allow the buyer to change?

  1. Its lots move to tighter sampling at receipt Check A
    Off the key. Tightened sampling is the response to a supplier whose lots start failing, the opposite of what a certification earns.
  2. Its parts go to stock without incoming inspection Check B
    This is the keyed answer. Certification means the buyer relies on the supplier's own process controls, so its lots can skip receiving inspection and move straight to stock.
  3. Its quality performance stops being tracked Check C
    Off the key. Certification is kept up through periodic audits and performance reviews, so tracking the supplier's quality continues after it is granted.
  4. Its parts no longer need any written specifications Check D
    Off the key. The written specifications stay in force; certification attests that the supplier meets them reliably, not that they stop applying.
You chose—
Key—
Outcome—

Study notes for this area: External supply

Using the explanations

A miss teaches more than a lucky hit, but only if you read the note. When your choice was wrong, check whether you misread the situation or simply did not know the term; the first calls for slower reading, the second for the matching section of the CPIM study guide, where every area has its own anchor.

For the calculation items, the explanation under the key sets out the arithmetic step by step. Redo the sum on paper and find the step where your figure parted from it. ASCM's handbook allows the calculator built into the testing software, plus a basic non-programmable one at test centers, so practice the sums on a plain calculator rather than a spreadsheet.

An independent question set, not ASCM's

The items started in existing exam-prep banks and were reworked for this site; none is copied from ASCM's Learning System or from the sample items in the content manual. Use the set to test your grip on the concepts of version 9.0; it does not preview the live exam forms.

On this page you see a raw percentage correct and nothing more. ASCM reports the real result on its own 200–350 range, passing at 300, and its conversion is not public, so no percentage here maps onto that range. On the live exam, 20 of the items are unscored trials that look like the others; the exam facts page has the detail.

Fact As the documents put it Source
Prep from ASCM The free CPIM Exam Content Manual, with outline, key terms, references and 10 sample questions, and the paid Learning System. ASCM offers a 30-day free trial of Learning System Module 1. CPIM ECM 9.01 CPIM program page2
Choices per question Four choices with one best answer, or a calculation from the data given. CPIM ECM 9.01
Items that count 130 scored questions that decide your result. CPIM ECM 9.01 ASCM chart 20263
Scoring approach Scaled, so forms of different difficulty are reported against one standard; there is no deduction for wrong answers, and a blank counts as wrong. CPIM ECM 9.01 ASCM scoring page4
Allowed in the room The on-screen calculator; at a center, also a simple non-programmable calculator, a print word-for-word translation dictionary and a clear water bottle. The ASCM Supply Chain Dictionary is not allowed. The water bottle rule began on November 2, 2026; none of the extras are allowed online. ASCM handbook 20265

From ASCM's CPIM Exam Content Manual 9.0, its CPIM program page (archived October 24, 2026), the exam details page (archived August 10, 2026) and the exam handbook of October 2026, checked November 18, 2026.

Documents behind this part: CPIM ECM 9.01 ASCM scoring page4 CPIM program page2 ASCM chart 20263 ASCM handbook 20265

Where to go after the set

More free sets on this site

Before you start the set

Do CPIM Part 1 and Part 2 practice questions still help with version 9.0?

Only in part. The two-part exam belongs to version 7.0 and is organized differently from the nine areas of 9.0. Many of the planning concepts carry over, but check each topic against the current content manual before you spend time on it.

Where can I find ASCM's own sample questions for the CPIM?

In the free CPIM Exam Content Manual, which includes sample questions next to the outline, key terms and references, and in the paid Learning System. They are ASCM's material, which is why none of them is reproduced here.

Which percentage on this test suggests I am ready to book?

No percentage here can promise a pass. The exam's cut is 300 on a scaled range, never stated as a share of right answers. Treat the area chips as a map of weak spots and close those before you book.

Documents behind this part: CPIM ECM 9.01 ASCM scoring page4 CPIM program page2

The study guide gives each content area of the manual its own section.