Here are 30 CSCP exam questions for ASCM's Certified Supply Chain Professional exam, free and without an account or a timer. They cover all eight main topics of version 5.0 of ASCM's content manual (ECM 5.0), the outline for exams through May 31, 2027, with items spread roughly in proportion to the topic weights. Choose an option and the explanation under every choice opens, so a wrong answer still teaches the distinction it was testing. 135
Items are spread roughly in proportion to the topic weights of ECM 5.0. The three heaviest topics, Manage Internal Operations and Inventory at 19% and sourcing and the customer and supplier relationships topic at 17% apiece, supply about half of the set; Evaluate and Optimize the Supply Chain, the lightest at 8%, supplies the fewest.
Every card shows its topic as a chip. After a full run, look at which chips your misses cluster under. The exam's own score report is organized the same way (your scaled score and result, with diagnostic feedback for each content section), so sorting your practice errors by topic shows where your next study hours should go.
Practice set: 30 questions across all eight topics
Tally: 0/30 tried, 0 on the key
I Demand · 10%Question 1 of 30
A manufacturer begins receiving point-of-sale data and joint forecasts from its key retail customers. Which effect is MOST likely?
Choose a letter to record your answer; each option then opens with its reasoning.
ALarger, less frequent orders from the retailersCheck A
Off the key. Bigger, lumpier orders are a source of amplification; information sharing pushes in the opposite direction.
BHigher safety stock needed at the manufacturerCheck B
Off the key. Better visibility lowers the uncertainty the manufacturer has to buffer, so the safety stock it needs falls rather than rises.
CLower total demand from end consumersCheck C
Off the key. Sharing data changes what the manufacturer sees, not how much consumers buy; total end demand stays where it was.
DLess demand amplification at upstream stagesCheck D
This is the keyed answer. When the manufacturer plans from actual consumer sales and a shared forecast instead of reacting to retailer orders, the swings that grow upstream shrink.
Baseline sales split 50% retail, 30% e-commerce and 20% wholesale. Past promotions lifted each channel over its own baseline: retail 25%, e-commerce 45%, wholesale 10%. If the promotional forecast is allocated by baseline channel shares rather than by each channel's lift, what is the MOST likely result?
AThe total promotional volume is overstatedCheck A
Off the key. The allocation rule only divides the forecast among channels; it does not change the total quantity forecast.
BToo little stock goes to retailCheck B
Off the key. Retail's 25% lift sits just below the 28% average implied by the shares, so a share-based split gives it slightly more than it will sell, not less.
CToo little stock goes to e-commerceCheck C
This is the keyed answer. Weighted by the baseline shares, the average lift is 0.5 × 25% + 0.3 × 45% + 0.2 × 10% = 28%; e-commerce lifts 45%, so a share-based split leaves it well short.
DToo little stock goes to wholesaleCheck D
Off the key. Wholesale lifts only 10% against the 28% average, so it receives clearly more promotional stock than it needs.
Demand history for an item shows sales rising by about 8 units a month, with the same peak every summer. Which forecasting approach is most appropriate?
AA qualitative forecast from sales and expert opinionCheck A
Off the key. Judgment methods fit situations without usable history; here the history shows a clear, repeating pattern that a quantitative model can capture.
BA simple three-month moving average of recent demandCheck B
Off the key. A short moving average lags behind a trend and flattens the seasonal peak instead of anticipating it.
CSimple exponential smoothing with a high smoothing constantCheck C
Off the key. A high constant makes simple smoothing react quickly, but with no trend or seasonal term it keeps chasing the pattern from behind.
DA time-series model adjusted for trend and seasonalityCheck D
This is the keyed answer. A steady monthly rise plus a repeating summer peak are a trend and a seasonal pattern, so the model needs a component for each.
II Network & information · 10%Question 4 of 30OTIF
A distributor reports a 96% fill rate but only 82% OTIF against a 95% target. Complaints concern late and partial deliveries. Where is the main problem most likely to lie?
AIn order execution at the shipping stageCheck A
This is the keyed answer. A high fill rate with low OTIF means stock is generally available; orders fail on timing and completeness while they are picked, packed and shipped.
BIn inventory availability across most SKUsCheck B
Off the key. A 96% fill rate shows that most demand is met from stock, so broad unavailability cannot explain the gap.
CIn the way the fill rate is calculatedCheck C
Off the key. Nothing suggests the fill rate is mismeasured; the two metrics capture different things, and OTIF is the one the complaints match.
DIn demand forecast accuracy for key itemsCheck D
Off the key. Poor forecasts would surface as stockouts and a lower fill rate; complaints about lateness point to a different stage.
A system monitors shipments against plan and automatically alerts the planner when a container misses its vessel cutoff. This capability is BEST described as:
Awarehouse management.Check A
Off the key. A WMS runs activity inside the warehouse, such as receiving, putaway and picking, not ocean shipments at a port.
Badvanced planning and scheduling.Check B
Off the key. APS builds plans and schedules against constraints; it does not track execution events in transit.
Cbusiness intelligence reporting.Check C
Off the key. Business intelligence analyzes historical data after the fact; it does not monitor execution in real time or raise exception alerts.
Dsupply chain event management.Check D
This is the keyed answer. Event management watches shipments against the plan and raises an alert when a milestone is missed, such as a vessel cutoff, so the planner can act.
Of 1,000 orders shipped, 40 were late, 25 were incomplete, 10 arrived damaged and 15 had documentation errors. Twenty orders had exactly two of these failures and none had more. What is the perfect order fulfillment rate?
A93%Check A
This is the keyed answer. Failures total 40 + 25 + 10 + 15 = 90, but 20 orders carry two of them, so 90 − 20 = 70 orders failed and 930 of 1,000 were perfect: 93%.
Failure instances
40 + 25 + 10 + 15
90
Orders with a failure
90 − 20 (orders counted twice)
70
Perfect orders
1,000 − 70
930
Perfect order rate
930 / 1,000
93%
B96%Check B
Off the key. 96% removes only the 40 late orders and ignores the incomplete, damaged and mis-documented ones, which also break a perfect order.
C91%Check C
Off the key. 91% subtracts all 90 failures as if each one were a separate order, counting the 20 orders with two problems twice.
D98%Check D
Off the key. 98% removes only the 20 orders with two failures, as if an order with a single failure were still perfect.
Which sourcing situation is LEAST suited to an online e-sourcing auction?
AStandard packaging bought in high volumeCheck A
Off the key. Standard, high-volume items with clear specifications are the classic auction case, because the bids are directly comparable.
BA complex service designed jointlyCheck B
This is the keyed answer. When the scope is worked out together with the supplier and hard to specify, bids cannot be compared on price alone, so negotiation fits better than an auction.
CA commodity chemical to a fixed specCheck C
Off the key. A fixed specification lets suppliers compete on price alone, so an e-auction suits a commodity like this.
DRepeat MRO items with clear specsCheck D
Off the key. Clearly specified repeat items can be put out to bid again and again with little risk, a good fit for e-sourcing.
Which purchasing tool is MOST appropriate for many low-value, one-off maintenance purchases, such as small tools bought from local stores?
AEDI purchase orders sent to each storeCheck A
Off the key. EDI needs an integrated trading partner and pays off on high, repeated volumes, not on one-off buys at local stores.
BProcurement cards with spending limitsCheck B
This is the keyed answer. P-cards let users buy small, unplanned items directly within set limits, which removes a purchase order for every low-value transaction.
CBlanket purchase orders with releasesCheck C
Off the key. Blanket orders suit repeated buys of known items from one supplier; one-off purchases from various local stores do not fit them.
DA formal quotation request for each itemCheck D
Off the key. A quotation request for every small tool costs more in effort than the item is worth.
A manufacturer designs a new component that embodies its proprietary technology and differentiates its product in the market. Which sourcing decision is MOST appropriate?
AMake it in-house to protect the core competencyCheck A
This is the keyed answer. A part that embodies proprietary technology and sets the product apart is a core competency, so keeping it in-house protects both the know-how and the advantage.
BOutsource it and protect the design by contractCheck B
Off the key. Contract terms limit misuse on paper, but the supplier still learns the technology; a contract does not keep a capability inside the firm.
COutsource it to the lowest-cost contract manufacturerCheck C
Off the key. Choosing on lowest cost treats a differentiating part like a commodity and hands its technology to an outsider.
DBuy it from several suppliers to keep prices competitiveCheck D
Off the key. Several sources spread the proprietary design even wider, and price competition is not the goal for a differentiating part.
A buyer cannot find any local source for a specialized coating, so it approaches a capable firm in an adjacent industry and persuades it to start supplying. This is an example of:
Aoutsourcing.Check A
Off the key. Outsourcing hands work the buyer used to do itself to an outside firm; the coating was never made in-house.
Bsupplier development.Check B
Off the key. Supplier development raises the capability of a firm that already supplies the buyer; this firm was not a supplier before.
Cearly supplier involvement.Check C
Off the key. Early supplier involvement brings a supplier into product design; it is not about recruiting a source where none exists.
Dreverse marketing.Check D
This is the keyed answer. Reverse marketing is the buyer taking the initiative to persuade a firm that has never supplied it to start doing so.
A company makes standard components to forecast in a lean flow and then finishes them to customer order in an agile flow. The point that separates the two flows is the:
Adecoupling pointCheck A
This is the keyed answer. The decoupling point separates forecast-driven, lean flow upstream from order-driven, agile flow downstream; strategic stock is held there.
Breorder pointCheck B
Off the key. A reorder point is the stock level that triggers replenishment of one item, not a structural point in the chain.
Cbreak-even pointCheck C
Off the key. Break-even is the volume at which revenue covers cost, a financial measure rather than a point in the material flow.
Dcontrol pointCheck D
Off the key. Control points are places where a process is monitored or scheduled, such as a bottleneck; the term does not mark the boundary between forecast and order.
Standard work for an assembly cell specifies the work sequence, takt time, and standard WIP. Its PRIMARY purpose is to:
Areduce variation and set an improvement baseline.Check A
This is the keyed answer. Writing down the best current sequence, takt time and WIP makes everyone work the same way, which cuts variation and gives improvement work a known starting point.
Bset piece-rate incentives for each cell operator.Check B
Off the key. Standard work describes how the job is done; it is not a pay scheme, and piece rates reward speed over the defined sequence.
Cremove the need for in-process quality inspection.Check C
Off the key. Standard work makes errors less likely, but it does not replace the checks built into the process.
Dfreeze the process and stop further change.Check D
Off the key. A standard is meant to be revised whenever a better method is found; it is the base for change, not a barrier to it.
A printer maker ships generic printers to regional distribution centers, where the country-specific power supply and manuals are added only after customer orders arrive. This practice is BEST described as:
Amass customization.Check A
Off the key. Mass customization tailors products to individual buyers at scale; adding one of a few standard country kits is a delay of differentiation, not individual tailoring.
Bkitting.Check B
Off the key. Kitting gathers parts into a set for an operation or an order; it does not describe delaying final configuration until demand is known.
Cpostponement.Check C
This is the keyed answer. Holding a generic printer and adding the country-specific power supply and manuals only after orders arrive delays differentiation, which is postponement.
Dspeculation.Check D
Off the key. Speculation is the opposite approach: products are finished to forecast and pushed toward markets before orders are known.
IV Operations & inventory · 19%Question 16 of 30TPM
Under total productive maintenance (TPM), which task is typically transferred to machine operators?
ADiagnosing complex electrical failuresCheck A
Off the key. Complex electrical faults need trained technicians; operators report symptoms rather than diagnose them.
BDaily cleaning, oiling and inspectionCheck B
This is the keyed answer. Autonomous maintenance gives operators the routine care of their machines, such as cleaning, lubricating and inspecting, so wear is spotted early and specialists can focus on harder work.
CMajor overhauls, rebuilds and retrofitsCheck C
Off the key. Overhauls and rebuilds are specialist jobs that maintenance staff plan and carry out.
DScheduling planned maintenance shutdownsCheck D
Off the key. Planned shutdowns stay with the maintenance function, which coordinates them with production.
A seasonal business calculates annual inventory turnover using only its year-end inventory balance, which falls at the seasonal low point. What is the effect on the reported ratio?
ATurnover is unaffected by which balance is usedCheck A
Off the key. The numerator covers the whole year, but the denominator is a single low snapshot, so the result does change.
BTurnover is overstated compared with using average inventoryCheck B
This is the keyed answer. Turnover is cost of goods sold divided by inventory; a year-end balance at the seasonal low is below the year's average, so the ratio comes out too high.
CTurnover is understated compared with using average inventoryCheck C
Off the key. Understatement would need a balance above average, such as one taken at the seasonal peak; the low point works the other way.
DThe direction depends on the inventory costing methodCheck D
Off the key. FIFO or LIFO changes the dollar value of the balance, but a balance taken at the seasonal low still sits below the year's average, so the bias keeps its direction.
A retailer's DC receives full truckloads from many suppliers and must sort them into mixed loads for stores within hours, without putting goods away. Which practice BEST fits?
ADrop shippingCheck A
Off the key. With drop shipping the supplier sends goods straight to the end customer, so nothing passes through the retailer's DC.
BBreak-bulk distributionCheck B
Off the key. Break-bulk splits one large shipment into smaller ones; it does not merge goods from many suppliers into mixed store loads.
CCross-dockingCheck C
This is the keyed answer. Cross-docking moves inbound loads across the dock into outbound store loads within hours, without putting goods into storage.
DFreight consolidationCheck D
Off the key. Consolidation combines small shipments into larger ones for the line-haul; it does not describe sorting inbound truckloads into store loads without storage.
A buyer imports a critical component from a politically unstable region. It wants the seller to bear transport risk until the goods arrive at its plant, ready for unloading, while the buyer handles import clearance and pays the duties. Which Incoterms® 2020 rule fits?
ADDPCheck A
Off the key. DDP would make the seller clear the goods for import and pay the duties, the tasks the buyer wants to keep.
BDAPCheck B
This is the keyed answer. Under DAP the seller bears the risk until the goods are at the named place, ready for unloading, while the buyer clears them for import and pays the duties.
CFCACheck C
Off the key. With FCA the risk passes to the buyer when the goods are handed to the carrier at the agreed place, typically in the seller's country, long before they reach the plant.
DCIPCheck D
Off the key. Under CIP the seller pays carriage and insurance to the destination, but the risk passes to the buyer once the goods are handed to the first carrier.
A seller shipping goods by sea wants to keep control of them until the buyer's bank pays under a letter of credit. Which document makes this possible?
AA certificate of originCheck A
Off the key. A certificate of origin supports customs and duty claims; it gives no control over release of the cargo.
BA commercial invoiceCheck B
Off the key. The commercial invoice states what was sold and at what value; it does not control who can collect the goods.
CA negotiable (order) bill of ladingCheck C
This is the keyed answer. An order bill of lading is a document of title: the carrier releases the goods only against it, and the bank hands it to the buyer when payment is made.
DA straight (non-negotiable) bill of ladingCheck D
Off the key. A straight bill consigns the goods to a named party and cannot be transferred, so it cannot serve as the title document a bank holds until payment.
A supplier receives a key customer's daily usage and stock data, decides when and how much to replenish, and keeps the customer's stock within agreed limits. This arrangement is:
Aconsignment inventory.Check A
Off the key. Consignment settles when the customer pays for stock held on its site, not who decides how much is replenished.
Bcollaborative planning, forecasting, and replenishment (CPFR).Check B
Off the key. CPFR rests on a forecast and plan that both partners agree on; here there is no joint plan, because the supplier alone reads the data and sets the replenishment.
Ca kanban pull system.Check C
Off the key. A kanban signal comes from the customer's point of use and tells the supplier exactly what to send; the supplier does not choose the quantity.
Dvendor-managed inventory (VMI).Check D
This is the keyed answer. In VMI the supplier sees the customer's usage and stock, decides when and how much to replenish, and keeps the stock between agreed limits.
A company wants one application to hold vendor scorecards, contract terms and collaboration records for all of its vendors. Which application fits BEST?
AEnterprise resource planning (ERP)Check A
Off the key. ERP processes transactions such as purchase orders and invoices, but it is not designed for scorecards and collaboration with vendors.
BSupplier relationship management (SRM)Check B
This is the keyed answer. An SRM application is organized around the supply base, keeping vendor scorecards, contracts and shared collaboration records in one place.
CWarehouse management system (WMS)Check C
Off the key. A WMS controls receiving, storage and picking inside a warehouse; it does not manage vendor relationships.
DCustomer relationship management (CRM)Check D
Off the key. CRM serves the demand side of the business; it is not built to manage vendors.
A buyer finds that supplier negotiations in China progress only after personal trust is built through introductions, repeated meetings and mutual favors. This reflects the concept of:
Akeiretsu.Check A
Off the key. Keiretsu are Japanese groups of firms linked by cross-shareholdings and long-term trading ties, a corporate structure rather than a personal-trust norm.
Bchaebol.Check B
Off the key. Chaebol are large Korean family-controlled conglomerates; the term describes ownership, not how negotiations build trust.
Cnemawashi.Check C
Off the key. Nemawashi is the Japanese practice of quietly building consensus among stakeholders before a formal decision, not the Chinese system of personal obligations.
Dguanxi.Check D
This is the keyed answer. Guanxi is the Chinese network of personal relationships and reciprocal obligations; business moves forward once that trust is in place.
Which change most directly raises first-contact resolution in a customer service center that handles order-status inquiries?
AAdd a callback queue for complex casesCheck A
Off the key. A callback queue guarantees a second contact for those cases, which lowers first-contact resolution by definition.
BGive reps live shipment and inventory visibilityCheck B
This is the keyed answer. Most order-status calls can be settled on the spot when the rep sees where the shipment is and what is in stock, so the customer needs no second contact.
CMeasure reps on calls handled per hourCheck C
Off the key. A calls-per-hour target pushes reps to end calls quickly, which tends to create repeat contacts rather than fewer.
DRoute delivery questions to the logistics teamCheck D
Off the key. Transferring each delivery question adds a handoff, so the first contact rarely settles the issue.
Which of the following measures would BEST indicate whether a company's supply chain risk management program is improving resilience?
AAnnual inventory turnoverCheck A
Off the key. Turnover measures inventory efficiency; higher turns can even mean thinner buffers against disruption.
BNumber of active suppliers per categoryCheck B
Off the key. A supplier count describes the structure of the supply base, not whether disruptions are handled better than before.
CAverage time to recover from a supply disruptionCheck C
This is the keyed answer. Resilience is the ability to absorb a disruption and recover from it, so recovery time measures the outcome directly.
DPercentage of customer orders delivered on time each monthCheck D
Off the key. On-time delivery reflects everyday performance and mixes many causes; it does not isolate how quickly the chain comes back after a disruption.
During the growth stage of a product's life cycle, what is the MAIN supply chain risk?
AInventory becomes obsolete as demand fallsCheck A
Off the key. Obsolescence belongs to the decline stage, when demand shrinks.
BThe market may not accept the productCheck B
Off the key. Uncertain acceptance is the risk of the introduction stage; by growth, the product has already caught on.
CCapacity falls short of rising demandCheck C
This is the keyed answer. In growth, demand climbs quickly, and the main risk is being unable to supply it, so capacity and supplier ramp-up come first.
DPrice competition squeezes marginsCheck D
Off the key. Margin pressure from rivals is typical of maturity, when demand levels off and competitors fight on price.
A manufacturer wants its supply base to recover quickly from disruptions without holding large idle inventories. Which approach BEST builds this capability?
ASuppliers able to shift output between plantsCheck A
This is the keyed answer. Flexible capacity across sites lets a supplier move production when one plant is hit, giving fast recovery without stockpiles.
BAnnual audits of each supplier's quality systemCheck B
Off the key. A quality audit checks how parts are made under normal conditions; it adds no spare capacity or alternative route for the supply base when a disruption hits.
CDoubling safety stock of purchased partsCheck C
Off the key. Doubling stock buys time, but it is exactly the large idle inventory the company wants to avoid.
DLonger fixed-volume contracts with each supplierCheck D
Off the key. Fixed volumes lock in quantities; they add commitment, not the ability to move or restore output.
Which of the following initiatives is an example of strategic supply chain redesign rather than tactical or operational improvement?
AMoving final assembly to a plant near the main marketCheck A
This is the keyed answer. Relocating an assembly stage changes the structure of the network, a long-term design decision and therefore strategic redesign.
BRenegotiating annual freight rates with current carriersCheck B
Off the key. New freight rates lower cost within the existing network, a tactical purchasing step.
CRecalculating safety stock for A-class itemsCheck C
Off the key. Recalculating buffers updates an operating parameter inside the current structure.
DMoving the S&OP meeting to a weekly cycleCheck D
Off the key. Changing a planning cadence alters how the current chain is managed, not how it is designed.
A buyer wants suppliers to disclose their environmental and social impacts using a common, comparable reporting framework. Which should it require?
AISO 26000Check A
Off the key. ISO 26000 offers guidance on social responsibility; it is neither certifiable nor a disclosure standard.
BISO 14001Check B
Off the key. ISO 14001 specifies a certifiable environmental management system; it sets no format for public impact disclosure and leaves social topics out.
CUN Global CompactCheck C
Off the key. The Global Compact is a set of ten voluntary principles that companies commit to, not a detailed disclosure framework that makes reports comparable.
DGRI StandardsCheck D
This is the keyed answer. The GRI Standards set out defined disclosures for economic, environmental and social impacts, so reports from different suppliers can be compared.
A buyer has selected a new supplier and signed the supply contract. Which stage of the supplier life cycle comes NEXT?
ASupplier qualificationCheck A
Off the key. Qualification checks capability and finances before a supplier is chosen; that stage ended when this supplier was selected.
BRelationship exit planningCheck B
Off the key. Exit plans belong to the end of a relationship, or are written into the contract terms, not to the step after signing.
COnboarding and integrationCheck C
This is the keyed answer. Once the contract is signed, the supplier has to be set up in the buyer's systems, told how orders, quality checks and communication will work, and linked into planning before deliveries start.
DPerformance review and developmentCheck D
Off the key. Reviews need a delivery record to measure, so they follow onboarding rather than coming straight after the signature.
On the version 5.0 exam you face 150 items in 3½ hours. Of those, 130 decide the outcome and 20 are unscored trial items hidden among them. ASCM reports the outcome on a scale, so the number you got right is never shown.
This set is shorter. Every one of its 30 items counts, no clock runs, and the result is a plain tally with no conversion behind it. Its job is diagnosis, showing which topics are weak, not predicting what you would score.
These items were reworked from exam-prep question banks that existed before this site, and they follow the format of the exam's items; they are not items from an ASCM exam form. ASCM's own sample questions are printed in its content manual, listed in the table below.
ASCM’s CSCP Exam Content Manual, with its outline, terminology, references and sample questions, plus the Learning System, sold separately. A 30-day free trial opens one Learning System module, Risk Response.
An optional purchase, separate from the exam: $1,450 for upgrade members, $2,015 otherwise. Access lasts 12 months and includes digital and printed books and a practice exam; it is not refundable.
From the version 5.0 content manual, the archived CSCP program page and ASCM's exam details page.
After the practice set
Practice for the other ASCM exam
Using this CSCP practice set
Are these real CSCP exam questions?
No. They follow the format of the exam's items, but they are not items from an ASCM exam form. Each one was reworked from an existing exam-prep bank and placed in one topic of version 5.0; the About page lists the review steps.
What does my tally on this set tell me?
Your tally here cannot be translated into ASCM's scaled result, so it says nothing about clearing 300. Treat the result as a map of topics: several misses under one chip point to a topic worth revisiting in the study guide.
Where can I find more CSCP practice questions?
ASCM prints sample questions in its content manual, and the Learning System, a separate purchase, adds a practice exam. A second, shorter set, with different items, closes the study guide.